top of page
Barren Beach_edited.jpg

Anton Larsen Bay

Mission:  Develop and promote stewardship, restoration and maintenance projects for trails.

Project Dates: June 2010-June 2014


Summary:  Over a period of 5 years ITN crews hardened with geoblock and provided three bridges along this 3-mile public easement trail connecting Anton Larsen Bay to Three Pillar Point.  Crews installed porous pavement to mitigate impacts to wetlands, reduce soil erosion and improve water quality.


Funding Partners:  Natural Resources Conservation Service

In-kind Partners:  Ouzinkie Native Corporation

bottom of page